JAKARTA, KOMPAS.com - The National Nutrition Agency (BGN) is working to resolve issues surrounding the development of 315 Nutrition Fulfillment Service Units (SPPG) funded by the 2025 State Budget (APBN).
The resolution process involves coordination with several related institutions and is based on audit results and regulations governing state financial management.
"The development of these 315 SPPG is being carried out by 74 contractors with contracts signed in October and November 2025," said BGN Spokesperson Tysa Novenny in a press statement on Wednesday (25/11/2026).
However, by the final deadline of December 31, 2025, no SPPG funded by the APBN has been declared complete.
At that time, the construction period was then extended for 90 days through a contract addendum, up to March 31, 2026.
"Up until the end of the extension period, some work remains incomplete by the contractors," Tysa noted.
Meanwhile, the budget for the 2025 fiscal year can no longer be utilized because the end-of-year holding account was rejected by the Ministry of Finance.
"We are committed to resolving the issues in the SPPG development using the 2025 State Budget. However, the resolution must be conducted meticulously," she stated.
The resolution process, according to Tysa, must comply with examination findings and adhere to regulations regarding state financial usage.
"We want to ensure every step taken is based on clear grounds and is accountable," Tysa added.
Under the leadership of Sudaryono, BGN is reviewing these issues.
Therefore, BGN met with the Ministry of Finance to discuss the provision of budget for the 2026 fiscal year.