JAKARTA, KOMPAS.com - Minister of Communication and Digital (Menkomdigi) Meutya Hafid responded to the halted construction of an AI-based data center by BDx in Jatiluhur, which was stopped by West Java Governor Dedi Mulyadi.
According to Meutya, the computing needs that require an AI data center should not disrupt public needs, particularly public services.
"So, we certainly have computational needs that require a data center. But at the same time, we must ensure that energy sufficiency is not compromised for other matters, especially for the public," said Meutya at the Komdigi Office in Central Jakarta on Wednesday (7/10/2026).
"We also cannot let water needs be disrupted. The way to balance this is by ensuring that various sectors communicate effectively," she added.
Meutya noted that the balance between the presence of data centers and public needs must be coordinated across various sectors.
She stated that coordination is necessary to determine permits and regulations prior to constructing a data center at a deemed suitable location.
"So, from Komdigi's perspective, we need to assess the current computational demands, the number of internet users, and identify locations with good connectivity where a data center could be appropriately sited. Therefore, location determination must also be established," she explained.
Previously, the construction of the AI-based data center by BDx, valued at IDR 3.5 trillion, in Jatiluhur, Purwakarta, West Java, could not proceed due to incomplete licensing processes.
West Java Governor Dedi Mulyadi emphasized that the temporary halt of the project does not mean the provincial government is rejecting investments in the region.
According to Dedi, construction cannot continue because the Building Construction Approval (PBG) and environmental impact analysis (Amdal) are not yet completed.
"I said to hold off on the implementation. The permits were not issued as of my visit yesterday. Where is the error? At the Purwakarta local government? No. The issue lies with the consultants who, by the time I visited, had not entered the data," he stated when met at the Merdeka Building in Bandung on Friday (2/10/2026).
Dedi said that he had already questioned the licensing issues with the company during a meeting on July 28, 2026.
However, three months later, the project requirements have still not been resolved.